Chapter 12.16 STORM WATER MANAGEMENT
Section 12.16.230 Performance bond/security.
The environmental services department may, at its discretion, require the submittal of a performance
security or bond prior to issuance of a permit in order to insure that the storm water practices are
installed
by the permit holder as required by the approved storm water management plan. The amount of the
installation performance security shall be the total estimated construction cost of the storm water
management practices approved under the permit, plus 25%. The performance security shall contain
forfeiture provisions for failure to complete work specified in the storm water management plan.
The installation performance security shall be released in full only upon submission
of the
written
certification by a registered professional engineer that the storm water practice has been installed
in
accordance with the approved plan and other applicable provisions of this chapter. The environmental
services department will make a final inspection of the storm water practice to ensure that it is in
compliance with the approved plan and the provisions of this chapter. Provisions for a partial pro-rata
release of the performance security based on the completion of various development stages can be done
at
the discretion of the environmental services department. (Ord. 2006-0098; 2002-1015)