Chapter 20.14 PLUMBING CODE
Section 20.14.230 Inspections.
Upon the completion of any installation or alteration of plumbing equipment for which a permit or license
is
required, the person, firm or corporation making the installation or alteration shall notify the inspection
services division, and an inspection of the installation or alteration shall be made within forty-eight
hours of
the time such notice is received, exclusive of Saturdays, Sundays and holidays, or as soon thereafter
as
practical. If the plumbing inspector shall find such installation or alteration in conformity with the
provisions of this code, the inspector shall approve the installation and authorize connection with
the supply
of water and/or natural gas. The plumbing inspector shall send an authorization to the agency supplying
the
water and/or natural gas service. If the authorization is issued for the installation, connection and
use of a
temporary service, the permit shall designate the time of expiration but may be revoked by the plumbing
inspector for cause before expiration. When any plumbing equipment is to be hidden or concealed from
view by the permanent placement of parts of the building, the person, firm or corporation installing
the
equipment shall notify the plumbing inspector and such equipment shall not be concealed until it has
been
inspected and approved or until forty-eight hours, exclusive of Saturdays, Sundays or holidays, shall
have
elapsed from the time of the notification; provided, that on any large installation, where the concealment
of
equipment proceeds continuously the person, firm or corporation installing such equipment shall give
the
plumbing inspector a minimum of 24 hours notice and inspection shall be made periodically during the
progress of the work. (Ord. 2000-9734)