Chapter 20.20 MECHANICAL CODE
Section 20.20.230 Inspections.
Upon the completion of any installation or alteration of mechanical equipment for which a permit or
license
is required, the person, firm or corporation making the installation or alteration shall notify the
inspection
services division, and an inspection of the installation or alteration shall be made within forty-eight
hours of
the time such notice is received, exclusive of Saturdays, Sundays and holidays, or as soon thereafter
as
practical. If the mechanical inspector shall find such installation or alteration in conformity with
the
provisions of this code, the inspector shall approve the installation and authorize connection with
the supply
of natural gas. The mechanical inspector shall send an authorization to the agency supplying the natural
gas
service. If the authorization is issued for the installation, connection and use of a temporary service,
the
permit shall designate the time of expiration but may be revoked by the mechanical inspector for cause
before expiration. When any mechanical equipment is to be hidden or concealed from view by the
permanent placement of parts of the building, the person, firm or corporation installing the equipment
shall
notify the mechanical inspector and such equipment shall not be concealed until it has been inspected
and
approved or until forty-eight hours, exclusive of Saturdays, Sundays or holidays, shall have elapsed
from
the time of the notification; provided, that on any large installation, where the concealment of equipment
proceeds continuously the person, firm or corporation installing such equipment shall give the mechanical
inspector a minimum of 24 hours notice and inspection shall be made periodically during the progress
of the
work. (Ord. 2000-9735)